| Project | Original estimated total costFootnote 1 | Revised estimated total costFootnote 2 | Actual cost totalFootnote 3 | 2013–14 ($ millions) |
Expected date of close-outFootnote 4 | |||
|---|---|---|---|---|---|---|---|---|
| Main Estimates |
Planned spending |
Total authorities |
Actual | |||||
| Program 1.2 Gateways and Corridors Sub-program 1.2.2 Gateways and Border Crossings Fund |
||||||||
| Detroit River Crossing - Project definition phaseFootnote 5 | 2,010.0 | 5,116.1 | 101.3Footnote 6 | 148.5 | 148.5 | 155.5 | 8.3Footnote 7 | 2020-2021 |
| Program 2.3 Environmental Stewardship of Transportation | ||||||||
| Fort Nelson Airport Environmental RemediationFootnote 7 - Project implementation stage | 20.4 | 35.7 | 31.2 | 1.4Footnote 8 | 1.4Footnote 6 | 1.4Footnote 6 | 1.4Footnote 6 | 2015-2016 |
| Program 4.1 Aviation Security Sub-program 4.1.4 Air Cargo Security Major Crown Project |
||||||||
| Canadian Air Cargo Security ProgramFootnote 5 – Final year | 600 | 153.6 | 68.9 | 14.8Footnote 9 | 14.8Footnote 9 | 14.8Footnote 9 | 8.8Footnote 9 | 2014-2015 |