Consultation results

This table was prepared by Transport Canada to facilitate the review of the comments received by stakeholders and the response of the Canadian Transit Company to these comments received as part of the public consultation process for the Ambassador Bridge Enhancement Project under the International Bridges and Tunnels Act. This table is published for information purposes only and is not intended to be an exact and exhaustive representation of all comments and responses received. The comments in this table do not represent Transport Canada positions or views.

The City of Windsor (main submission)

Comment/Concern CTC Response
1. The IBTA Application fails to comply with federal law: the CTC has not satisfied conditions precedent to the issuance of federal approval – notably whether the Canadian Transit Company is obligated to comply with the 1921 Canadian Transit Company Act (CTC Act) and is prohibited from constructing or operating the ABEP without first having complied with sections 10 and 11 of the CTC Act. The Bridge was approved by resolution by The Town of Sandwich and adopted by the City of Windsor in 1928.

2. Transport Canada should require compliance with municipal law or defer processing the IBTA application pending decision of the Federal Court including the Federal Court’s consideration and interpretation of the following:

  • The CTC Act and Property Standards By-law as it applies to the ABEP , whether or not there is any conflict between the Property Standards By-lay and the CTC Act and whether the CTC Act already sets out a complete code for addressing any identified conflicts;
  • Whether there is merit to the assertion that homes slated for demolition as part of ABEP are immune from municipal laws on constitutional grounds;
  • The obligation set out in the CTC Act which expressly requires compliance with municipal law.
It is the CTC ’s position that all authority needed is within the CTC Special Acts and any authorization needed from the City of Windsor in in the 1928 Authorization by the Town of Sandwich and adopted by the City of Windsor.
3. Processing an incomplete application undermines the U.S. approach Processing an application in Canada does not undermine the process in United States. The DIBC / CTC continues to work toward approvals in the United States concurrently with the process in Canada. The United States Coast Guard is the lead agency for the approval of the environmental studies and they have been provided with all documents and studies that have been requested.

4. The IBTA application fails to comply with IBTA Guidelines and violates the IBTA subsection 7(2) including:

  1. Failing to provide information on existing and proposed traffic to be carried by the bridge, including information on the effect the traffic will have on the existing road system and nearby communities;
  2. Failing to examine local impacts beyond the bridge and plaza;
  3. Failing to identify mitigation measure required to address the ABEP ’s adverse impacts; and
  4. Failing to provide a list of the regulatory approvals that must be obtained in relation to the project.

The final Environmental Impact Statement (EIS) with appendices and attachments as well as the Environmental Assessment Screening Report (EASR) were attached to and are part of the IBTA Application and address all of the comments listed below.

  1. Traffic is discussed in great detail in Section 3.5 beginning on page 27 of the EIS .
  2. The EIS was conducted in accordance with the Revised Federal Environmental Assessment Guidelines under the Canadian Environmental Assessment Act for the Ambassador Bridge Enhancement Project, which was prepared by Transport Canada and Windsor Port Authority in Consultation with the Federal EA Review Team. For the purposes of impact assessment, the study area examined extended approximately 200 metres (657 feet) from the proposed Project footprint. Depending on the factors identified in the section 16(1) of the CEAA and the EA Guidelines dated August 2007 the area of impact assessment did vary according to the study being undertaken and the spatial extent of the potential environmental effects.
  3. Mitigation measures for all resources are identified throughout Section 5.0 and 7.0 of the EIS as well as their respective appendices. The mitigation measures are also described and in Table 6.2 of the 2013 Draft EASR . Required mitigation and follow-up measures are identified in the January 2014 Environmental Assessment Screening Report.
  4. Section J of the IBTA application outlines all the approvals needed in the United States and their status. Similarly, Section K of the IBTA Applications outlines additional approvals required in Canada.
5. There are unassessed nassessed potential adverse environmental impacts of the ABEP . There are no unassessed potential adverse environmental impacts of the ABEP . Please refer to the EIS and EASR previously approved by Transport Canada and the Windsor Port Authority along with the CTC .
6. The IBTA application is premature as missing studies could alter the ABEP ’s design. There are no missing studies. The final design will be tailored to meet the commitments, mitigation and monitoring as directed in the final EASR issued by Transport Canada and the Windsor Port Authority in February 2014.
7. Missing information, including information on air quality and mitigation for noise impacts, prevents the formulation of appropriate terms and conditions

No information is missing since the EIS and EASR were appended to the IBTA application.

Air quality and associated mitigation are discussed in Sections 4.1, 5.1, 6.3.1, 7.1, and 7.9.1 of the EIS as well as Appendix D. It is further discussed and summarized in Section 6.1 of the EASR .

Noise and Vibration and associated mitigation are discussed in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5 of the EIS as well as Appendix J. It is also discussed and summarized in Section 6.11 and 6.12 of the EASR .

All commitments, mitigation and monitoring is summarized in Table 6.2 of the 2013 draft EASR issued by Transport Canada and the Windsor Port Authority.

The City of Windsor’s Traffic Analysis Peer Review

Comment/Concern CTC Response
1. The IBTA application is premature due to missing comprehensive traffic study, and requires a comprehensive traffic study to show the extent of impacts on Windsor streets and traffic safety.

As described in Section 1.2.1 on page 3 of the EIS , the purpose of the project is to;

  • Improve the structure to facilitate the movement of vehicles and ensure the continued free flow of goods between Canada and the United States;
  • Upgrade the efficiency through the provision of FAST/NEXUS lanes;
  • Meet current highway standards; and
  • Preserve the existing Ambassador Bridge structure.

Traffic numbers used in this report were taken from the approved DRIC project. There are three relevant reports that were posted on the DRIC website at http://www.partnershipborderstudy.com/. The first report, “Detroit River International Crossing Study Travel Demand Forecasts” was completed in September 2005 and established the total cross border unconstrained travel demand. The projected traffic volumes in the study are based on the estimated demand for travel across the river and are not constrained. While these volumes have been shown to overestimate the actual volumes, nevertheless, these volumes were conservatively used in the assessment and mitigation of impacts by the ABEP . The remaining posted reports deal with the distribution of the demand based traffic and were used to demonstrate that the introduction of FAST lanes at the Ambassador Bridge could capture a small number of long haul trucks that may otherwise use the Blue Water Bridge. These were shown to increase the traffic volumes by much less than 2% as discussed in Section 3.5 of the EIS . Further, the volumes projected in the 2006 DRIC Travel Demand Forecast have been shown to dramatically over estimate the actual traffic with the 2014 DRIC projected volume being 78.4% greater than the actual volume. Nevertheless, the CTC used these highly over optimistic projections in assessing impacts and determining mitigation for the ABEP .

As such, it is the CTC ’s position there are no measurable impacts on Windsor City Streets and traffic safety as a result of the ABEP . Any changes to the city streets beyond those already discussed in the EIS , EASR and IBTA Permit Application are beyond the scope of the project.

2. The IBTA application fails to evaluate the impact of ABEP on crossing efficiency.

The existing plaza has numerous inspection booths dedicated to FAST trucks and NEXUS users only. The introduction of dedicated FAST lanes thru the entire facility with the ABEP will move participants through these trusted trader/traveler programs more efficiently. As participation in the FAST and NEXUS program increases, waiting times are expected to be reduced as these program participants will not have to wait in line with other non-participants. Bus traffic will also benefit through the use of designated lanes allowing them to bypass regular passenger vehicle traffic and proceed directly to the CBSA secondary inspection facility.

In addition, the ABEP provides an additional 12 commercial primary inspection booths which nearly doubles the processing capacity for trucks from existing conditions.

3. The IBTA application fails to assess the environmental effects of the future traffic volumes projected to cross the Ambassador Bridge on Huron Church Road and other City streets in Windsor. See response to comment # 1 above.
4. The IBTA application fails to assess the potential traffic and environmental impacts in Windsor that would be caused by the long back-ups of vehicles on the ABEP and approach roads to the ABEP . See response to comment # 1 above.
5. Truck volumes along Huron Church Road are projected to more than double while passenger car volumes are projected to increase less than half as much according to the DRIC study and ABEP EIS . Impacts associated with the shift to a greater share of trucks in the vehicle composition crossing the Ambassador Bridge have not been adequately addressed in the IBTA application. See response to comment # 1 above.
6. Truck traffic impact onto local Windsor streets has not been explored even though there will be four million more trucks per year. See response to comment # 1 above.
7. Community impacts have not been analyzed especially with truck volumes at the Ambassador Bridge expected to double. All community impacts resulting from the project have been analyzed and assessed in accordance with the scoping document. The findings and mitigation is presented in the EIS and EASR .
8. The IBTA application is deficient for failing to discuss or assess the environmental impacts of the total vehicle crossing capacity that the ABEP can provide itself, or the greater vehicle crossing capacity that will exist when both the ABEP and the existing Ambassador Bridge are simultaneously in service. See response to comment # 1 above. The full demand based unconstrained traffic volumes were conservatively used to assess and mitigate impacts which will not change regardless of the number of lanes operational.
9. The CTC ’s IBTA application fails to evaluate the current design of the E.C Row Expressway/Huron Church Road/401 interchange, and the potential impacts that the ABEP would have on that interchange and consequently on roads within the City.

It is the CTC ’s position that the ABEP will have no effect on these roadways and interchanges since the build and no build traffic volumes are less than 2% different.

See # 1

10. ABEP has an operational lifespan of 100 years, but the CTC has considered the impacts of the project for just five years post-construction. The IBTA application must be considered incomplete until a reasonable assessment of project impacts is carried out, one that considers potential impacts not only during the period of construction but also for at least 20 years of operation.

The temporal boundaries for the project were determined by the Revised Federal Environmental Assessment Guidelines Under the Canadian Environmental Assessment Act for the Ambassador Bridge Enhancement Project, which was prepared by Transport Canada and Windsor Port Authority in Consultation with the Federal EA Review Team.

The temporal boundary for most analyses included present day, construction (2013-2015) and operation (any time after 2015). The air and noise analyses required a future build date to be analyzed to discern impacts. The air quality analysis identified year 2015 as the construction date and year 2025 as the future operation build year. The noise study identified 2010 as the existing year (for current traffic noise impacts) and 2025 as the future operation build year.

11. The Ambassador Bridge’s assessment horizon of five years from completion is way below other horizon years for similar projects which use a planning horizon of 15-28 years post construction. See response to comment 10.
12. The IBTA application is deficient for failing to adequately assess other reasonable viable build alternatives, such as rehabilitating (or widening) the current bridge in place, or rehabilitating and reconfiguring the existing approach ramps to be used by both spans. These build alternatives have the potential to significantly decrease or avoid some of the ABEP ’s significant negative impacts on the local community, including to heritage structures, and merit assessment before the IBTA application is processed. Other alternatives are discussed and evaluated in detail in Section 1.2 of the EIS . Alternatives to the ABEP failed to achieve the project objectives.
13. There are additional deficiencies in the IBTA application, including that the noise assessment used 2010 traffic volumes to model noise and vibration impacts on Windsor City streets in 2025. For traffic noise, a worst case scenario would assume the maximum amount of free flowing traffic at the highest speed (considered level of service C) as opposed to constant queuing on the bridge. Therefore, the assumption of constant queuing on the bridge and plaza were not used for the traffic noise study.
14. The IBTA application indicates that an investment grade analysis was performed for the ABEP ; the CTC has not released the study as part of the application for the city to evaluate. The CTC did not use this investment grade analysis as part of the environmental assessment process or for the IBTA application. The CTC elected to conduct the assessment of the impacts using the higher traffic volumes presented by the DRIC study in order to ensure more than sufficient mitigation measures were implemented.

15. If the Ambassador Bridge truly believes in its traffic estimates it should have no problem accepting safeguards to keep traffic at or near that level. SSE recommends the following measures:

  1. The CTC should institute a pricing plan on the Ambassador Bridge.
  2. If the CTC rejects the pricing proposal, then the City should implement a pricing plan.
CTC sets its tolls according to established policies.

The City of Windsor’s Noise and Vibration Peer Review

Comment/Concern CTC Response
1. The IBTA application is incomplete. Without the proper studies on noise and vibration, conditions cannot be identified.

The final Environmental Impact Statement (EIS) with appendices and attachments as well as the Environmental Assessment Screening Report (EASR) were attached to and are part of the IBTA Application and address all of the comments listed in this Peer Review.

A detailed noise and vibration study was conducted on the project and can be found in Appendix J and summarized throughout the EIS in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5. It is also discussed and summarized in Section 6.9 of the EASR . Table 6.2 of the 2013 draft EASR contains a summary of the mitigation, commitments and monitoring required.

2. The CTC fails to examine the ABEP ’s noise impacts on the community. In order for the CTC to provide a complete application to TC pursuant to the IBTA , suitable for review by TC and key stakeholders, it must include the following elements, currently missing from the CTC application:

  • Consideration of the noise impacts that ABEP may cause as a result of increased traffic on approach roads and on local roads that require relocation to service the project;
  • Use of adequate and representative sensitive receptors within the community;
  • Use of realistic traffic data over a reasonable planning and assessment horizon;
  • Adequate collection of baseline noise data, compliant with industry standards and Ministry of the Environment and Climate Change guidelines;
  • Consideration of road surfaces (ie. grooved concrete);
  • Consideration of construction impacts; and
  • Application of appropriate noise standards for assessment.
This comment is a summary of comments 3-12 regarding noise and vibration. Please see response to comments 3-12.
3. A proper noise and vibration study must consider the noise impacts of ABEP traffic on local roads and relocated roads.

Local roads and proposed modifications to local roads were considered in the noise and vibration study.

The noise and vibration study can be found in Appendix J and summarized throughout the EIS in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5. It is also discussed and summarized in Section 6.9 of the EASR .

4. A proper noise and vibration study must use representative residential and sensitive receptors within the affected community. Figure 2 of the Noise study found in Appendix J of the EIS shows the location of all receptors studied. In addition, Table VII of the noise study found in Appendix J of the EIS provides a description of each receptor. The assessment has considered 34 receptors which represent over 100 residential, institutional and Heritage buildings in the study area.
5. A proper noise and vibration study must use consistent traffic data to assess ABEP ’s noise impacts on the bridge, plaza and local roads. Noise from approach roads and from the plaza and bridge should both be assessed using consistent traffic volumes for a minimum of 10 years, and preferably for 20 years from commencement of operations (not the start of construction), as is commonly done for highways. The noise and vibration study was conducted in accordance with the Revised Federal Environmental Assessment Guidelines Under the Canadian Environmental Assessment Act for the Ambassador Bridge Enhancement Project, which was prepared by Transport Canada and Windsor Port Authority in Consultation with the Federal EA Review Team. The years used were consistent with this scoping document.
6. A proper noise and vibration study must include adequate baseline measurement. In context of this project, to both establish statistically meaningful ambient sound data and to calibrate the acoustic modeling, continuous sound monitoring for a minimum of one week, with hourly data summaries should be done. Measurements in the field were conducted only to assist with calibrating the acoustical model of the bridge to be representative of both the existing (no build) and future scenarios. It is the CTC ’s position that more extensive monitoring would not provide additional information for that purpose.
7. A proper noise and vibration study must consider road surface type. The CTC acknowledged that different road surfaces cause different sound level emissions, but assumed without assessment that the proposed sound barriers would mitigate the impacts of a grooved concrete surface. This assumption is inappropriate. Noise impact and mitigation assessments should have been done based on the correct source emission source. The noise and vibration study for the project was completed in accordance with the Revised Federal Environmental Assessment Guidelines Under the Canadian Environmental Assessment Act for the Ambassador Bridge Enhancement Project, which was prepared by Transport Canada and Windsor Port Authority in Consultation with the Federal EA Review Team. Further, the noise and vibration study was conducted using applicable standard practices and information available at that time.
8. A proper noise and vibration study must consider the mitigation of construction impacts in addition to operational impacts. An assessment of potential noise and vibration impact in the community should be done now, even if preliminary, together with a realistic assessment of the performance of potential/proposed mitigation. This would allow formulation and stakeholder review of conditions for construction procedures and mitigation, if necessary and appropriate, as part of the IBTA approvals process. Leaving an impact assessment until the work is underway, as proposed by the CTC through the federal screening and IBTA application, is not appropriate. Construction noise and vibration were considered in the EIS . Please refer to Appendix J of the EIS . A Noise Management Plan is currently being drafted. An outline of this plan is included in the EIS in Sections 5.9, 5.18, and 7.5. A CTC representative will be accessible at all times and appointed as the community contact to address any questions, concerns or complaints during construction. As part of the Noise Management Plan, CTC will retain an expert to address noise related complaints or concerns and conduct any necessary field work related to noise during construction, when necessary. The Community Consultation Plan will also include at least one public meeting prior to construction and a public website with project information and information on how to comment on the Project.
9. A proper noise and vibration study considers noise impacts over 24 hours, including the impact of noise and night. Noise from traffic is expected to be the same or less at night as during the day time hours, when there is more traffic. Noise intensive construction items such as pile driving will be limited to daylight hours and will meet the requirements of the local noise ordinances.
10. Consideration of noise from truck engine brakes. The only mitigation proposed by the CTC to date is to put the trucks in the middle lane, put quieter vehicles in the outer lanes, “as much as possible”, and use the roadside barrier and outer lanes to provide shielding. The City of Windsor has a bylaw prohibiting the use of engine brakes and the CTC will continue to do its best to encourage people to not use jake brakes. However, CTC does not have the authority to levy fines or other measures to prevent the use of engine braking as that is the purview of the City of Windsor. CTC is willing to work cooperatively with the City of Windsor in eliminating the use of jake brakes when it is not required. In any case, the noise walls that will be installed as part of this project will serve to reduce noise levels over the no build alternative.
11. The proposed noise/vibration mitigation is inadequate. Until the CTC is required to submit a complete noise assessment study, it is not possible for stakeholders to provide meaningful comment on the appropriate terms and conditions to be imposed as part of any IBTA approval. The CTC should be required to complete and resubmit the IBTA application after having addressed the deficiencies noted herein. A detailed noise and vibration analysis was conducted for the project as part of the EIS . Further, Section 6.9 and Table 6.2 of the 2013 draft EASR contain detailed requirements needed during final design and construction.
12. There is a need for compliance verification/monitoring. The CTC has deferred preparing these programs and has not provided the relevant details either as part of the federal screening or as part of the IBTA application. During the final design and construction phase, the CTC has committed to developing a Community Consultation Plan. An outline of this plan is included in the EIS in Sections 5.9, 5.18, 7.5 and 7.9, which is of sufficient detail to provide meaningful comment. It is further explained in Table 6.2 of the EASR .

The City of Windsor’s Air Quality Assessment Peer Review

Comment/Concern CTC Response

1. The IBTA application is premature and incomplete without the following two key submissions:

  1. Design mitigation: the CTC application should be considered incomplete until detailed plans have been provided that allows stakeholders to review proposed traffic flow and air quality mitigation details.
  2. Air quality follow-up program should include the following elements:
    • Traffic levels could be more than double than those predicted by the CTC , resulting in air quality impacts that exceed the maximum modeled by the CTC .
    • The proportion of truck traffic to passenger vehicle traffic could change, resulting in a significant change in air quality impacts.
    • The project could cause traffic volumes on local roads to grow, impairing service at local intersection and roads and resulting in deteriorating air quality.
    • Use of outdated emission software (U.S EPA Mobile 6 rather than the new U.S EPA MOVES model) could underestimate the air quality impacts of stop and go traffic.
    • Queuing times could exceed those estimated by the CTC , causing longer line ups and a deterioration of air quality.
    • Road and bridge surfaces may not be maintained as assumed in the EIS emission rates resulting in increased air emissions.
    • Background air quality may change.

1. Information used in the analyses is provided in Appendix D of the EIS . Air quality and associated mitigation are discussed in Sections 4.1, 5.1, 6.2.2, 6.3.1, 7.1, and 7.9.1 of the EIS as well as Appendix D. Mitigation strategies are specifically discussed in Section 7.1. The commitments, mitigation and monitoring is further described and summarized in table 6.2 of the 2013 draft EASR .

2. Refer to Section 3.5 of the EIS for a detailed discussion of the traffic. Also, please refer to the response to comment # 1 made by the City of Windsor’s Traffic Analysis Peer Review.

For purposes of evaluating the environmental impacts of the ABEP , including air quality, a worst-case scenario was used. Specifically, the entire projected demand-based volumes from the DRIC studies were used without reduction. These unconstrained demand-based volumes were then inflated by the entire additional volume predicted to be captured from the Blue Water Bridge and the Detroit- Windsor Tunnel by the DRIC Level 2 and 3 Analysis. Based on these conservative assumptions, an upper bound 2030 volume using the ABEP is established at 7,358,000 trucks and 9,113,000 cars for a total of 16,471,000 vehicles.

The EIS was conducted in accordance with the Revised Federal Environmental Assessment Guidelines Under the Canadian Environmental Assessment Act for the Ambassador Bridge Enhancement Project, which was prepared by Transport Canada and Windsor Port Authority in Consultation with the Federal EA Review Team. This document included the use of Mobile6. The new EPA model, MOVES, was not an approved model when the air quality study was conducted. This project was grandfathered in using Mobile6.

Reasonable and conservative queuing times were assumed in the modeling. In order to conservatively compare the no build and build alternative air quality impacts, the same assumptions were used in the build and no build alternatives even though the project is expected to result in reduced wait times as a result of the introduction of FAST/NEXUS dedicated lanes.

CTC is committed to maintaining road and bridge surfaces as described in the Mitigation Compliance Monitoring and Follow-up program.

Background air quality is expected to improve in the future due to more stringent fuel and vehicle emission standards and improved vehicle engines.

2. Following submission of a complete application, which has been circulated to stakeholders for review and comment, the following two areas should be considered in the Terms and Conditions of Approval of the IBTA license.

  1. Monitoring program: ongoing air quality monitoring is the only method to ensure that predicted air quality impacts are met, and if not, an air quality management program must be in place that is rigorous and detailed to ensure that air quality levels predicted in the EIS are met and air quality does not further deteriorate and provide a risk to nearby residents.
  2. Containment material: a procedure must be developed as a license Term and Condition to ensure that if contaminated material is found prior to or during construction, that a proper plan be in place to ensure appropriate mitigation and air quality measurements are undertaken to ensure local residents are not exposed to harmful and unsafe level of contaminants.

A complete application including the attachments ( EIS with attachments and EASR ) has been circulated in which all of the comments have already been investigated and assessed as explained below.

  1. Please see previous responses regarding the mitigation and follow up program for air quality. Once again, please refer to Sections 5 and 7 of the EIS along with Table 6.2 of the EASR with clearly describe the monitoring program required.
  2. Contaminated materials are discussed in section 5.14 and 7.3.1.7 of the EIS and Table 6.2 of the 2013 draft EASR . As stated, if contamination is discovered during construction, it will be evaluated in accordance with the guidance provided by the Ontario Environmental Protection Act (R.S.O. 1990), and Ontario Regulation 153/04 Record Site Condition.
3. The City of Windsor must be recognized as an ongoing stakeholder in reviewing and commenting on all aspects the review of the detailed design and development of the Air Quality Follow-Up Program and Monitoring Programs. As well, the City needs to be recognized in these programs as a key stakeholder and reviewer in the ongoing air quality monitoring program and the air quality follow-up plan. The CTC has agreed to establish an advisory committee to provide leadership, oversight and guidance on the project. The City of Windsor has been recognized as a stakeholder to be part of this advisory committee.

The City of Windsor’s Land Use Planning and Socio-Economic Impacts Related to the Proposed ABEP

Comment/Concern CTC Response
1. Potential heritage impacts on the existing Ambassador Bridge structure: the proposal to have a second span adjacent to the existing Ambassador Bridge will have detrimental impacts on the heritage values of the 1929 structure itself. In the U.S, the bridge is considered eligible for the National Register of Historic Places. This eligibility restricts the use of Federal-sources funds for undertakings that could diminish its heritage character. The Ambassador Bridge is eligible for listing on the United States National Register of Historic Places. The proposed bridge concept has been approved in the United States by the State Historic Preservation Officer (SHPO) and the Advisory council on Historic Preservation (ACHP) with a memorandum of agreement signed by all parties. Design measures have been incorporated to mitigate potential adverse effects and reduce impacts to the historic character of the existing Ambassador Bridge. The design of the proposed structure will incorporate non-specular materials into the design of the project components to decrease reflectivity and visibility of project features. The new span is designed to meet the U.S. Secretary of the Interior Standards for Rehabilitation 3, 9 and 10 to be consistent with the historic status of the Ambassador Bridge.
2. The CTC has not considered the heritage impacts on the neighbouring community of Sandwich and University Campus area.

The Olde Sandwich Towne Community Improvement Plan and The Sandwich Heritage Conservation District Conservation Plan Final Report are dated October 2012, published well after the development of the August 2007 “Revised Federal Environmental Assessment Guidelines Under the Canadian Environmental Act for the Ambassador Bridge Enhancement Project (2006)” and after the completion of much of the environmental analysis associated with the ABEP . However, the issues associated with these planning documents were given consideration as part of the EIS and the EASR , particularly within Appendix N of the EIS . This analysis was performed by a professional engineer with a significant history and experience of supporting the cultural heritage initiatives and preservation in the City of Windsor. Detailed interior and exterior evaluations of buildings on the east side of Indian Road were conducted. A secondary purpose of the investigation by this qualified individual “was to assess whether these properties [on the east side of Indian Road] enhance or diminish the Heritage Conservation objectives of the Phase 1 Sandwich Heritage Conservation District Study.” Consideration was given to the Sandwich Heritage Conservation District Study.

No heritage sites will be demolished or moved during the construction of the Project. A total of 17 houses will be demolished to accommodate the proposed plaza expansion. Two building will be demolished to accommodate the bridge expansion and a total of 73 houses will be demolished within the project area to create a buffer area between the bridge and the community to the west. As described in Appendix N, the interior and exterior of these houses were investigated to document the condition of their structural, mechanical and electrical systems. All houses were deemed unfit for re-occupancy due to vandalism and structural deficiencies. The assessment concluded that none of the houses merit a historical or heritage designation based on established Provincial, National, and International guidelines. Detailed discussions on the heritage sites can be found in Section 4.11, 5.11.1., 6.2.3, and 7.6 of the EIS .

3. The land in the vicinity of the Ambassador Bridge has more potential to contain archaeological resources than any other land in the city. Any development should be subject to an archaeological condition to conduct further studies and have them approved by the Ontario Ministry of Tourism, Culture and Sport. A Stage 1, 2 and 3 archaeological study were conducted as part of the project. These studies can be found in Appendix M and are summarized in the EIS in Sections 5.12 and 7.7. Potential mitigation options and procedures are outlined as well. One site was found to require a Stage 4 investigation and will take place prior to and then during the construction. The CTC is working closely with the Walpole Island First Nations (WIFN) on this effort and both WIFN and the Ontario Ministry of Tourism, Culture and Sport will be consulted on Stage IV mitigation prior to construction.
4. The CTC has failed to acknowledge potential effects on the community, including local businesses. The proposed ABEP lies within an area that has been identified as socially and economically challenged, and any changes in terms of property access, traffic disruptions, changes in traffic patterns, can have devastating effects on the local socio-economic conditions in the area. Social impacts of the proposed project were discussed at length in Sections 4.10, 4.11, 4.12, 6.2.3, 5.10, 5.11, 5.13 and 7.6 of the EIS as well as Appendices M and N. Changes to community cohesion are specifically addressed in Section 7.6.7 of the EIS . The ABEP will utilize vacant property currently owned by the proponent and located directly adjacent to the existing operation. In order to support the implementation of the Ambassador Bridge Plaza Master Plan Study, residential areas adjacent to the existing plaza were purchased. Social features will not be displaced and disruptions were considered. There will be no displacement of businesses but rather, economic activity will be supported by the ABEP . Access to businesses will remain at all times.

5. Assessing other land use and socio-economic impacts of the ABEP :

  • Potential changes on land use and traffic patterns.
  • Potential changes on community resources, including parks, waterfront access, and public safety.
  • Protection of community and neighbourhood characteristics.
  • Maintain consistency with existing planned land use.
  • Protect cultural resources.

A thorough and comprehensive EIS has been prepared for the project studying and assessing potential impacts of the project on land use. The construction of the proposed replacement span directly adjacent to the existing bridge will clearly have no significant environmental effect on land use, schools, playgrounds, sports fields and places of worship as shown in the EIS and EASR and as discussed in the responses to comments above. The majority of the project is being constructed where other major transportation land uses have been historically occurring including the existing Ambassador Bridge, Huron Church Road, Indian Road and the Windsor Plaza.

Community and cultural resources were considered in the EIS in Sections 5.10, 5.11, 5.12, 5.13, 7.6 and 7.7 as well as Appendix M and N. Section 7.6.7 specifically describes how the project will not have an impact on parks, waterfront access, and neighborhood characteristics. It also describes how the project is consistent with the various local plans including the City’s Greenway / Recreation way System and Bicycle Use Master Plan and the City of Windsor Official Plan.

Safety was considered in a number of ways including safety of motorists, border safety, and safety within the adjacent communities. As an eighty-six year old structure, the existing Ambassador Bridge does not reflect modern highway standards for lane and shoulder widths. The lack of safety shoulders on the Ambassador Bridge causes significant disruptions in the flow of traffic when a vehicle breaks down or an accident occurs. The replacement span is proposed to be constructed with safety shoulders on both sides of the outer travel lanes. The proposed Project will increase traffic safety and operations and will reduce vehicular accidents within the project limits.

In addition, a green space will be developed between the plaza and the nearby community of Sandwich on the east side of Indian Road, providing additional green space for the community.

The City of Windsor’s Office of the City Engineer

Comment/Concern CTC Response
1. Environmental impact, the spills of toxic materials. City engineering staff is concerned about significant effects on the environment as well as public health and safety arising from accidental spills of fuel and other hazardous and toxic materials. The Spills Prevention and Contingency Plan in Appendix C of the EIS as well as Section 6.13 of the EASR , contains the best management practices to minimize the likelihood of a spill. Spills of hydrocarbons or other hazardous materials will be handled in accordance with applicable regulations and procedures and in full compliance with all legislative requirements. All pollutants and runoff will be collected in a system located on the bridge and carried to the treatment system.

2. The City have the following concerns about the CTC ’s failure to adequately assess the environmental impacts that could be caused by the accidental spill of toxic materials:

  • No information is provided in the EIS or DSR about the number of trucks transporting dangerous goods or the classes (and volume) of dangerous goods that will be transported across the ABEP ;
  • No information is provided in the EIS or DSR about the number of accidents on the Ambassador Bridge or previous accidents involving dangerous goods on similar bridges to estimate the number of potential accidents that will occur on the ABEP and to assess the environmental impacts of those accidents;
  • There is no assessment of the environmental effects of spills of dangerous goods caused by collisions or other types of accidents on the new ABEP in the EIS or the DSR;
  • The City is concerned that spills of dangerous goods during the operation of the ABEP will cause significant adverse environmental effects and health impacts.
See response to Comment 1.
The CTC has failed to acknowledge storm water impacts on city sewers and the Detroit River. City staff is concerned that significant adverse environmental impacts will be caused by the permanent increase in storm water runoff and flow from the ABEP . Section 3.4 of the EIS describes the two alternatives that will be considered during final design for storm water. In addition specific details are described in Appendix E of the EIS pertaining to Draft Erosion and Sediment Control and Storm water Management Plan. Appendix E discusses extensively the design measures during construction including the Ontario Provincial Standards for Roads and Public Works prepared by the Ontario Ministry of Transportation and Municipal Engineers Association. It also discusses the operation phase being designed in accordance with the applicable regulatory standards (MOE Storm water Management Planning and Design Manual). It is also recognized that the storm water management design will target an enhanced treatment level.
There has been no consideration or assessment of the impacts of the ABEP on City utilities and services in the EIS or DSR. The environmental impact of re-routing the sewers has not been assessed. No re-routing of sewers is anticipated by the project.

McDonald’s Restaurants of Canada Limited (Huron Church location)

Comment/Concern CTC Response
1. No formal public meetings or information sessions have been held, particularly with regard to how the project will affect roads, traffic flows and local businesses.

Section 7.10 and Appendix O of the EIS summarizes the extensive public involvement conducted to date. Consultation with the public regarding the proposed Project has been ongoing for several years. Representatives of the proposed Project have reached out to the community since 2005 to discuss and review the proposed Project. Four public information sessions were held from April 16 – 19, 2007.

In addition, the EASR was published for public comment from April 12, 2013 to June 7, 2013.

2. The project information does not include detailed drawings of how local property owners will be impacted or include details on property impacted, traffic flow, restrictions in proposed ingress/egress, expropriation of lands from property owners, road widening, business loss in the community, and timing of the project. Negative consequences for property owners have not been identified or addressed. Environmental impacts for the closure of Huron Church Road (HCR) were evaluated and included in the mitigation in the EIS for the ABEP . However, HCR closure is not part of the project as proposed in the IBTA application. Should the closure of HCR be considered by the CBSA as prudent, it would only be implemented once all required approvals are obtained and an agreement can be reached between the property owners and the CTC . During the final design of this small portion of the project, the CTC would consult with all affected property owners and arrive at a mutually agreeable solution before proceeding with construction.
3. There appears to be a new roadway or tunnel to be created between the adjoining Mikhail Holdings lands and the McDonald’s lands, as illustrated in the CTC reports. It appears that this will either be an entrance or exit from the new bridge. No information has been provided on mitigation, expropriates or lands or setback requirements. This is neither an exit nor entrance from the bridge. It is an extension of Indian Road in the event that HCR is closed. Also see response above.
4. Significant realignment/relocation of Huron Church Line will affect historical traffic patterns. See response to # 3
5. McDonald’s and Mikhail Holdings will apparently lose the entrance/exit with full turning movements to and from College Ave, which is currently shared between the two sites. McDonald’s access will not be affected. See responses above.
6. The McDonald’s lands will apparently lose full turning movements to and from College Avenue, resulting in a right-in, right-out only, from the McDonald’s lands. See response to # 5
7. Traffic leaving the bridge will not be able to access the restaurant as they will not be able to turn left into its site. See response to # 5
8. College Avenue apparently will be widened, which means some of the McDonald’s lands will have to be expropriated. See response to # 5
9. Issues with access, noise, vibration, pollution and impact during construction period and after the project is completed, which will have significant and detrimental impacts on restaurant operations and sales, have not been addressed. See response above. All other construction occurs north of the railroad and will have little or no effect on McDonalds Lands.
10. A detailed comprehensive project plan that addresses the implications of the project and mitigation strategies should be made available to the public. These are included in Chapters 5 and 7 of the EIS and Table 6.2 of the EASR .

Mikhail Holdings Limited

Comment/Concern CTC Response
1. The proposal does not include sufficient detail regarding how property owners in the surrounding areas will be able to continue operating without negative consequences on their operations. No information has been provided with respect to traffic flow or planned mitigation of introducing a new 6 lane highway into the neighbourhood.

The new six lane facility is elevated from the border to the existing plaza and will not change the way the local roads function.

Environmental impacts for the closure of Huron Church Road (HCR) were evaluated and included in the mitigation in the EIS for the ABEP . However, HCR closure is not part of the project as proposed in the IBTA application. Should the closure of HCR be considered by the CBSA as prudent, it would only be implemented once all required approvals are obtained and an agreement can be reached between the property owners and the CTC . During the final design of this small portion of the project, the CTC would consult with all affected property owners and arrive at a mutually agreeable solution before proceeding with construction.

2. Mitigation measures such as fences, berms, landscaping and setbacks have not been specified. These items will be specified and detailed in the final design in accordance with the mitigation requirements described in Sections 5 and 7 of the EIS and Table 6.2 of the Screening Report.
3. Sufficient meaningful community consultation has not taken place and potentially affected property owners have not been contacted regarding the proposed plans. Proponents should undertake a period of full public consultation on their initiative. During the final design phase of the project when the precise property needs are identified, the CTC will consult with property owners recognizing that a suitable agreement will need to be developed.
4. Access to properties and changes to community traffic patterns have not been studied or addressed in the proposal. See responses above. Traffic patterns and volumes on the relocated Huron Church Road are studied and presented in Appendix Q of the EIS .
5. Property owners directly impacted by the proposed re-routing of Huron Church Road (through their parking lot) have not been consulted. Environmental impacts for the closure of Huron Church Road (HCR) were evaluated and included in the mitigation in the EIS for the ABEP . However, HCR closure is not part of the project as proposed in the IBTA application. Should the closure of HCR be considered by the CBSA as prudent, it would only be implemented once all required approvals are obtained and an agreement can be reached between the property owners and the CTC . During the final design of this small portion of the project, the CTC would consult with all affected property owners and arrive at a mutually agreeable solution before proceeding with construction.
6. There is a need for a discussion of options and alternatives for the project. See response to # 5
7. The proposed project has an undersized footprint in relation to crossings with similar capacities. The proposal should more accurately reflect the lands actually required to adequately meet the needs of inspection agencies, the community and nearby landowners. Appendix B of the EIS includes the Ambassador Bridge Plaza Master Plan Study which was undertaken, with input from the CTC and the CBSA , to develop plaza alternatives that could accommodate a future increase in traffic volumes.

Kevin Flood and Anne-Marie Laniak (Lance Homes)

Comment/Concern CTC Response
Please identify properties located in the project footprint and clarify addresses of buildings to be demolished. All properties entirely or partially within the project footprint, as shown in Figure 2 of the IBTA application, will be demolished.
5.5 meter high perimeter fencing is redundant and should be reduce to a maximum height of 4 meters. A 5.5 metre high noise barrier is proposed along the western extent of the customs inspection plaza. Noise modeling suggested that a shorter barrier wall would not provide the noise reduction desired.
There is a need for increased understanding of the level of nighttime construction, especially during the final exam period for University of Windsor students.

Little or no construction is anticipated at night. Certainly, noise intensive construction items such as pile driving will be limited to daylight hours and will meet the requirements of the local noise ordinances.

As part of the commitments found in Section 5.19 of the EIS and Table 6.2 of the EASR , CTC commits to coordinating with schools within 300 m of the Project to create a mutually agreeable construction system to reduce the impact of noise on schools especially during exams.

A plan for street closures, specifically with respect to Donnelly and Peter Streets, should be identified. Suggestion that only one street be closed at a time during construction and that both streets remain permanently open to vehicle and pedestrian traffic when the project is completed. During final design, a maintenance of traffic plan will be developed for the construction of the Project that the CTC believes will require only short term closures for erection of girders and other activities overhead. No more than one street will be closed at a time and all streets will remain open when project is complete.
Request that the Huron church Road re-alignment be completed and follow a linear route on the eastern edge of the Forster High School Track. The proposed realignment of Huron Church Road, if implemented, will traverse on the eastern side of the track.
What traffic calming solution will be proposed for the corner of Wyandotte Street and Indian Road?

A detailed traffic discussion can be found in Section 3.5 and Appendix Q of the EIS . The traffic analysis was performed as a part of this study in order to evaluate the impacts of the project of local roads. As a result of this study, additional improvements were identified that will be needed for the operation of the study intersections at an acceptable level of service. These additional needed improvements are listed below:

  • Signalization of the intersection of Indian Road at Wyandotte Street.
  • Signalization of the intersection of Indian Road Extended at College Avenue.
  • Conversion of the eastbound shared right-through lane for the intersection of Huron Church Road at College Avenue to an exclusive right turn lane.

Our Lady of the Assumption Catholic Parish

Comment/Concern CTC Response
The impact of the proposed project on the character of the neighbourhood and quality of life of people who reside in the area west of Huron Church Road has not been adequately considered.

A thorough and comprehensive EIS has been prepared for the project studying and assessing potential impacts of the project on land use. The construction of the proposed replacement span directly adjacent to the existing bridge will have no significant effect on land use, schools, playgrounds, sports fields and places of worship as shown in the EIS and EASR and as discussed in the responses to comments above. Mitigation will be implemented as required by Sections 5 and 7 of the EIS and Table 6.2 of the 2013 draft EASR .

Community and cultural resources were considered in the EIS in Sections 5.10, 5.11, 5.12, 5.13, 7.6 and 7.7 as well as Appendix M and N. Section 7.6.7 specifically describes how the project will not have an impact on parks, waterfront access, and neighborhood characteristics. It also describes how the project is consistent with the various local plans including the City’s Greenway / Recreationway System and Bicycle Use Master Plan and the City of Windsor Official Plan.

The proposal has not taken into consideration the likely increase in volume of traffic on local roads (particularly Huron Church Road) and associated traffic and safety issues that would result from the project. It is the CTC ’s position that the difference between the build and the no build traffic volumes is minimal.
A study of the potential impact of vibration from construction and from increased bridge traffic on the Assumption Church heritage structures should be undertaken. A detailed noise and vibration study was conducted for the project that specifically included an analysis of Assumption Church. Noise and Vibration and associated mitigation are discussed in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5 of the EIS as well as Appendix J. Mitigation requirements are described in Table 6.2 of the EASR .

The Windsor-Essex Catholic District School Board

Comment/Concern CTC Response
The contemplated construction can be expected to negatively impact students attending two schools located within one block of the proposed construction area (St. Michael Catholic high School and Assumption College Catholic High School).

Noise intensive construction items such as pile driving will meet the requirements of the local noise ordinances.

As part of the commitments found in Section 5.19 of the EIS , CTC commits to coordinating with schools within 300 m of the Project to create a mutually agreeable construction system to reduce the impact of noise on schools especially during exams.

The operation of the bridge will create on-going noise problems for the schools and safety issues associated with increased traffic and potential falling debris from the bridge. A detailed noise and vibration study was conducted on the project and can be found in Appendix J and summarized throughout the EIS in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5. With the proposed mitigation in place, the CTC expects noise to be reduced at many locations during operation due to bridge design features.

Lisa Gretzky, MPP Windsor West

Comment/Concern CTC Response
The neighbourhood of Olde Sandwich Towne will experience increased traffic volumes and congestion and the neighbourhood was not built to withstand heavy passenger vehicle and commercial traffic. The CTC ’s position is that the difference between the build and the no build traffic volumes is minimal. The streets through the neighbourhood of Olde Sandwich Towne will experience no change in volume.
Increased congestion will impede access to local businesses and the University of Windsor. It is the CTC ’s position that traffic volumes on the local roads around the University of Windsor will not be changed by the ABEP . Access to businesses will remain at all times.

Brian Masse, MP Windsor West

Comment/Concern CTC Response
The proposed project potentially encroaches onto residential housing south of College Ave that is currently occupied and functional. No encroachment occurs to housing south of College Avenue.
The project should not proceed until the active zoning dispute between the City of Windsor and CTC is resolved. It is the CTC ’s position that all authority needed is within the CTC Special Acts and any authorization needed from the City of Windsor is in the 1928 Authorization by the Town of Sandwich and adopted by the City of Windsor.
While the project proposes to re-route traffic through a functional neighbourhood in close proximity to schools and other neighbourhood amenities, the proposal does not provide enough information to gauge the potential impacts of the project on the surrounding neighbourhood. Social impacts of the proposed project were discussed at length in Sections 4.10, 4.11, 4.12, 6.2.3, 5.10, 5.11, 5.13 and 7.6 of the EIS as well as Appendices M and N. Changes to community cohesion are specifically addressed in Section 7.6.7 of the EIS .
Concerns about whether appropriate alternatives to the proposed project have been considered and what consideration has been given to the alternative of upgrading the existing span. Other alternatives are discussed and evaluated in detail in Section 1.2 of the EIS . Alternatives to the ABEP failed to achieve the project objectives.
The required storm water management system has not been fully described. Section 3.4 of the EIS describes the two alternatives that will be considered during final design for storm water. In addition specific details are described in Appendix E of the EIS pertaining to Draft Erosion and Sediment Control and Storm water Management Plan. Appendix E discusses extensively the design measures during construction including the Ontario Provincial Standards for Roads and Public Works prepared by the Ontario Ministry of Transportation and Municipal Engineers Association.
Details of mitigation measures for environmental impacts (for example mitigation measures for noise) of the project should be made available for public comment. Mitigation is discussed at length for all resources throughout Sections 5.0 and 7.0 of the EIS and associated appendices. Further a commitments table is outlined in Section 5.19. All mitigation and commitments are described and summarized in the EASR that was published by TC and the Windsor Port Authority for public comment from April 13, 2013 to June 7, 2013.

Sutts, Strosberg Lawyers

Comment/Concern CTC Response
The proposed project will unduly disrupt and displace the historic community of Sandwich.

Social impacts of the proposed project were discussed at length in Sections 4.10, 4.11, 4.12, 6.2.3, 5.10, 5.11, 5.13 and 7.6 of the EIS as well as Appendices M and N. Changes to community cohesion are specifically addressed in Section 7.6.7 of the EIS .

The majority of the project is being constructed where other major transportation land uses have historically occurred including the existing Ambassador Bridge, Huron Church Road, Indian Road and the Windsor Plaza. All construction of both the plaza expansion and the second span will take place on property directly adjacent to the existing operation and on right of way already owned by the proponent with zero required relocations.

The proposed project requires either the expansion of existing Windsor local roads leading to the Ambassador Bridge or the conversion of some of these roads into a dedicated freeway, which would have a negative impact on local Windsor traffic. The difference between the build and the no build traffic volumes is minimal. It is the CTC ’s position that the streets through the neighbourhood of Olde Sandwhich Towne will experience no change in volume.

Walpole Island First Nation

Comment/Concern CTC Response
1. There remain outstanding concerns with respect to Archaeological Stage IV issues. CTC and Walpole Island First Nation (WIFN) are preparing an agreement with respect to archaeological issues. Walpole Island First Nation will also be a part of the Community Consultation Committee.
2. There remain outstanding concerns with respect to direct consultation with the Walpole Island First Nations peoples during design, construction and operations. See response to # 1
3. There remain outstanding concerns with respect to Aboriginal title and rights issues. See response to # 1

Comment/Concerns from the General Public

A total of 409 submissions were received from members of the general public:

  • 65 expressed support for the proposal, including 11 who supported the proposal on condition that the existing bridge be dismantled.
  • 344 submissions expressed opposition to the proposal.

Similar comments and concerns were raised across these submissions. Issues raised have been consolidated in the following list:

Comment/Concern CTC Response
The proposed bridge approach and expanded customs plaza within the boundaries of the Sandwich community will encroach on residential areas deteriorating the social, historical, and cultural makeup of a community already in significant need of revitalization.

Social impacts of the proposed project were discussed at length in Sections 4.10, 4.11, 4.12, 6.2.3, 5.10, 5.11, 5.13 and 7.6 of the EIS as well as Appendices M and N. Changes to community cohesion are specifically addressed in Section 7.6.7 of the EIS .

The majority of the project is being constructed where other major transportation land uses have been historically occurring including the existing Ambassador Bridge, Huron Church Road, Indian Road and the Windsor Plaza. All construction of both the plaza expansion and the second span will take place on property directly adjacent to the existing operation and on R/W already owned by the proponent with zero required relocations.

There has been no assessment of the socio-economic effects of the ABEP on local community. Social impacts of the proposed project were discussed at length in Sections 4.10, 4.11, 4.12, 6.2.3, 5.10, 5.11, 5.13 and 7.6 of the EIS as well as Appendices M and N.
Adequate consultation with the community has not been undertaken. Section 7.10 and Appendix O of the EIS summarizes the extensive public involvement conducted to date. The EASR for the project was published by TC and the Windsor Port Authority for public comment from April 13, 2013 to May 13, 2013.
A new 6 lane bridge will likely increase traffic volumes resulting in increased congestion and safety concerns on Huron Church Road. It is the CTC ’s position that the difference between the build and the no build traffic volumes is minimal.
Truck traffic will continue to travel through the City of Windsor on the local road network and will have air quality, noise and vibration implications as well as an impact on the health and quality of life of citizens.

Air quality and associated mitigation are discussed in Sections 4.1, 5.1, 6.2.2, 6.3.1, 7.1, and 7.9.1 of the EIS as well as Appendix D. Noise and Vibration and associated mitigation are discussed in Sections 4.9, 5.9, 6.2.2, 6.3.2, and 7.5 of the EIS as well as Appendix J.

With the proposed mitigation, CTC expects traffic noise levels to be the same or less than current levels.

Details of the air quality study can be found in Section 7.1 and Appendix D of the EIS and Section 6.1 of the EASR .

Table 11 on page 42 of 56 of the air quality report contained in Appendix D of the EIS summarizes the maximum air quality concentration results for all of the studied pollutants. As shown in this table, there were PM10 exceedances already occurring in the background concentrations, during the construction and during the operation scenarios. All other pollutants are within compliance for all scenarios (construction and all operation scenarios). For the PM10 exceedances, there is no difference between the build and the do nothing scenario. Rigorous and comprehensive mitigation measures will be implemented as described in Table 14 in Section 5.19 of the EIS . The effectiveness of this mitigation will be confirmed through a comprehensive compliance monitoring and adaptive management plan as discussed in the EIS and in Table 6.2 of the EASR .

There is no highway connecting the Ambassador Bridge to Highway 401 and the proposal relies on the City of Windsor to provide and maintain the local road network required to connect the proposed bridge to the highway system. CTC seeks to improve the performance and operation of the facility it owns. Changes to the actual traffic volumes thru the ABEP are minimal.
Twinning the bridge will not result in increased efficiency because truck and car traffic will still need to travel on Huron Church road. The CTC is improving the operation of the facility it owns or controls. The introduction of the shoulders on the new bridge will greatly improve safety and the FAST/NEXUS lanes will improve operations by reducing wait times on the bridge. It is the CTC ’s position that since traffic volumes will not materially change as a result of this project, efficiency will not be decreased on Huron Church Road. The CTC would be happy to engage with the TC and the City of Windsor on how to improve efficiency outside the limits of the facility it owns.
Additional capacity is not needed at this crossing location. The project is not meant to increase capacity at the border, but instead replace an aging structure with one that will meet all the current safety standards and provide for more effective FAST truck and NEXUS vehicle processing.
Increased traffic from the project will create increased health and safety issues along Huron Church Road, particularly for students at eight different schools along the corridor (including the University of Windsor Campus, composed of over 15,000 students, as well as Assumption College Catholic Secondary School with a student population of over 700 students). It is the CTC ’s position that the project does not increase traffic on Huron Church Road. The project simply improves safety and reduces idling time within the ABEP facility.
The project footprint is located on a culturally sensitive area for both First Nations and early Euro-Canadian History, and includes designated archeological sites. The proponent has engaged the First Nations and is actively working with them on additional archeological investigations. Stage 1, 2 and 3 archaeological studies were conducted as part of the project, found in Appendix M and are summarized in the EIS in Sections 5.12 and 7.7. One area requires a stage 4 investigation which will take place prior to and then during the construction in consultation with the Walpole Island First Nations (WIFN).