Project | Original estimated total costFootnote 1 | Revised estimated total costFootnote 2 | Actual cost totalFootnote 3 | 2013–14
($ millions) |
Expected date of close-outFootnote 4 | |||
---|---|---|---|---|---|---|---|---|
Main
Estimates |
Planned
spending |
Total
authorities |
Actual | |||||
Program 1.2 Gateways and Corridors
Sub-program 1.2.2 Gateways and Border Crossings Fund |
||||||||
Detroit River Crossing - Project definition phaseFootnote 5 | 2,010.0 | 5,116.1 | 101.3Footnote 6 | 148.5 | 148.5 | 155.5 | 8.3Footnote 7 | 2020-2021 |
Program 2.3 Environmental Stewardship of Transportation | ||||||||
Fort Nelson Airport Environmental RemediationFootnote 7 - Project implementation stage | 20.4 | 35.7 | 31.2 | 1.4Footnote 8 | 1.4Footnote 6 | 1.4Footnote 6 | 1.4Footnote 6 | 2015-2016 |
Program 4.1 Aviation Security
Sub-program 4.1.4 Air Cargo Security Major Crown Project |
||||||||
Canadian Air Cargo Security ProgramFootnote 5 – Final year | 600 | 153.6 | 68.9 | 14.8Footnote 9 | 14.8Footnote 9 | 14.8Footnote 9 | 8.8Footnote 9 | 2014-2015 |