Program 1.2 Gateways and Corridors
Sub-program 1.2.2 Gateways and Border Crossings Fund
Project | Original Estimated Total Cost 1 | Revised Estimated Total Cost 2 | Actual Cost Total 3 | 2012-13 | Expected date of close-out 4 | |||
---|---|---|---|---|---|---|---|---|
Main Estimates | Planned Spending | Total Authorities | Actual | |||||
Detroit River Crossing – Project definition phase 5 |
2,010.0 |
3,390.0 |
92.9 6 |
70.7 |
70.7 |
72.1 |
38.2 7 |
2020-21 |
Program 2.3 Environmental Stewardship of Transportation
Project | Original Estimated Total Cost 1 | Revised Estimated Total Cost 2 | Actual Cost Total 3 | 2012-13 | Expected date of close-out4 | |||
---|---|---|---|---|---|---|---|---|
Main Estimates | Planned Spending | Total Authorities | Actual | |||||
Fort Nelson Airport Environmental Remediation 8 -
|
20.4 |
35.7 |
29.7 |
0.9 9 |
0.96 |
0.96 |
0.96 |
2015-16 |
Program 4.1 Aviation Security
Sub-program 4.1.4 Air Cargo Security Major Crown Project
Project | Original Estimated Total Cost 1 | Revised Estimated Total Cost 2 | Actual Cost Total3 | 2012-13 | Expected date of close-out 4 | |||
---|---|---|---|---|---|---|---|---|
Main Estimates | Planned Spending | Total Authorities | Actual | |||||
Canadian Air Cargo Security Program5 |
600.0 |
153.6 |
60.1 |
14.6 |
14.6 |
14.6 |
10.1 |
N/A |
Footnotes
[1] Very first Treasury Board Expenditure Authority decision for total project cost. (Return to footnote 1 source paragraph)
[2] Most recent Treasury Board Expenditure Authority decision for total project cost. (Return to footnote 2 source paragraph)
[3] All expenditures to date including the current year (Return to footnote 3 source paragraph)
[4] Fiscal year (Return to footnote 4 source paragraph)
[5] Employments Benefits Plan, accommodation and costs for the Canada Border Services Agency are included in the “Original Estimated Total Cost” and the “Revised Estimated Total Cost” columns only. These costs are excluded from the amounts indicated in the other columns. (Return to footnote 5 source paragraph)
[6] Previous year costs have been adjusted to include all costs, including corporate support costs that were included in the Total Estimated Costs. (Return to footnote 6 source paragraph)
[7] Numbers include the Gateways and Border Crossings Fund expenditures related to the Windsor Essex Parkway. (Return to footnote 7 source paragraph)
[8] Numbers exclude GST and Employee Benefits Plan. (Return to footnote 8 source paragraph)
[9] 85% funded by Federal Contaminated Sites Action Plan in 2012-13. (Return to footnote 9 source paragraph)