FINA - Bill C-15, An Act to Implement certain provisions of the budget tabled in Parliament on November 4, 2025 - February 02, 2026

f. If pressed on Consultations with Indigenous Communities

Issue/Source: High-Speed Rail initiative (Co-Development phase)

Location: Ontario and Quebec

Date: January 2026

If pressed on consultations with Indigenous communities

  • Consultations began early and will continue on an ongoing basis with Indigenous communities along the proposed corridor with respect to their rights and interests.

Background Information

The co-development phase between Alto and the private development partner, Cadence, is a consortium compromised of Canadian and French companies. This phase of work began in March 2025.

It is too early to determine a specific cost for the Alto High-Speed Rail project. However, initial estimates are between $60 - $90 billion.

The Alto High-Speed Rail initiative is an example of the Government transforming and restructuring the Canadian economy. It will revolutionize how people live and work in Ontario and Quebec by halving journey times, decreasing emissions and unlocking opportunities for jobs and housing. It will also spur economic growth while supporting Canadian industries and suppliers.

The initiative will join major centres through Canada’s most densely populated areas, and yield benefits for key government priorities such as:

  • Housing – Alto will contribute to the housing supply with a target of 63,000 units.
  • Environment – Alto will provide a sustainable means of travel – with a target of 25 million tonnes of carbon dioxide (CO2) emissions savings.
  • Job creation – Alto will deliver well-paying jobs – with a target of 51,000 new jobs over ten years.

The initiative will support Canadian businesses by maximizing their participation. Benefits will come through sourcing goods and material such as steel, timber and concrete as well as investment and partnerships.

The project will require 300,000 tonnes of steel.  Alto has already commenced work on maximizing the sourcing of this material from domestic suppliers.

Alto has been consulting over 40 Indigenous leaders, communities and organizations through Ontario and Quebec since 2022, and is seeking ways to for Indigenous peoples to significantly participate in the initiative and share its benefits.

In January 2026, Alto launched a corridor-wide public consultation campaign, which will continue until spring 2026. The consultation campaign will focus on introducing the corridor to Canadians in Ontario and Quebec, including Indigenous peoples. The results of this consultation will be included in a multi-criteria analysis to recommend a preferred route and station locations to the Minister for approval. Once this process is complete, the preferred route will be shared publicly by Alto.