Question & Answer | Category |
---|---|
CostsHow much has Transport Canada spent on the rail bypass project to date?As of April 2022, Transport Canada has spent approximately $19 million on the project. These costs include expenditures related to the development of engineering plans and environmental and technical field studies. A material order of approximately $11 million has also been placed. |
costs |
CostsWhat will the total project costs be?Total project costs are not available at this time. Transport Canada is working with Canadian Pacific to put together a revised cost estimate for the project. Current market conditions, such as rising material costs and supply chain issues, and project components have evolved since the last estimate in 2018. COVID-19 has also had an effect on some of these factors. Moreover, refined engineering designs and results of the geotechnical studies allowed a better understanding of the project scope and requirements. It has become now necessary to revise the project's construction costs during the plans and design phase, which is currently underway. As part of the 2022 federal budget, $237.2 million was allocated to Transport Canada in addition to the previously allotted funds. These financial resources will be distributed over five years, starting in 2022-2023, for the construction of the Lac-Mégantic rail bypass, dismantling of the existing track, and implementation of environmental measures. At this time, the Government of Canada will continue to advance elements of the project while a cost-sharing agreement with the Government of Quebec is reached. |
costs |
Transport Canada’s public consultationWill the January/February 2022 and October/November 2022 public consultation report be shared with the public?The Transport Canada consultation report for the January/February 2022 has been submitted to the Canadian Transportation Agency (CTA). The consultation report for the October/November 2022 will be submitted to the CTA in the coming months. Both reports will be made public once the CTA considers it finalized and complete. |
consultation |
Transport Canada’s public consultationHow can I access documentation on studies conducted for this project?To request a copy of project studies, please contact the project team at TC.InfoLacMegantic.TC@tc.gc.ca. Please note that confidential information must remain protected. |
consultation |
Rail SafetyHow will bypass safety be ensured?Canadian Pacific (CP) is designing and constructing the bypass. CP will carry out the project in accordance with all applicable regulatory requirements. For example, it will design, build and operate the bypass in accordance with Transport Canada’s Rules Respecting Track Safety. As CP indicates, bypass will be built with new materials, including new rails and ties. Transport Canada will continue to conduct regular inspections to ensure that rail operations and infrastructure on the new bypass comply with the rules. |
rail |
Rail SafetyHow has Transport Canada improved rail safety and the transport of dangerous goods in recent years?Transport Canada has significantly strengthened its oversight program. It also has put in place regulatory and legislative reforms that included stronger measures and requirements to protect communities living along railway lines. For example:
|
rail |
Rail SafetyHow fast will the trains be travelling on the bypass?The bypass is designed in accordance with Class 3 standards. According to Transport Canada regulations, the maximum permitted speed is 40 mph. However, trains can also operate at lower speeds because several factors can affect the actual speed of a train circulating on a particular track. These may include physical characteristics, such as terrain, slope,curvature, and temperature. The conductors may also consider other operational factors, such as the density of rail traffic, to determine the speed of a train. Railways are responsible for the safety of their rail operations and must determine the safe operating speed at all locations on a track. |
rail |
Rail SafetyHow long will the trains using the bypass be?The construction and implementation will not determine the frequency or length of the trains operated by CP in the Lac-Mégantic area. Client demand and traffic volumes will determine the length and frequency of the trains. Frequency and length depend on economics and the needs of rail shippers, such as Tafisa in Lac-Mégantic. According to the common carrier obligations set out in the Canada Transportation Act, CP must accept with reasonable conditions all traffic that it is asked to transport. |
rail |
Rail SafetyCan Transport Canada regulate train length or weight?Transport Canada regulates and monitors underlying factors that determine train length and weight. For example, according to these underlying safety rules, railway companies:
Railway companies must ensure that their rail operations are safe and comply with all regulatory requirements. Transport Canada conducts inspections to ensure that railway companies are complying with the rules. |
rail |
Rail SafetyCan you provide concrete examples of regulations that have been improved in recent years to strengthen railway safety and the transportation of dangerous goods in Canada?Transport Canada has significantly strengthened its oversight program. It also has put in place regulatory and legislative reforms that included stronger measures and requirements to protect communities living along railway lines. For example, it includes:
|
rail |
LandsHow will you ensure that private water sources (wells) are not compromised or contaminated?Access to safe drinking water is essential. We will ensure that citizens with a private well retain access equivalent to what they currently have. Several measures will be implemented:
All these measures will be at no cost for the private well owners. |
lands |
ConstructionThe construction of noise reduction walls are being planned as part of this project. Will these completely cut off the noise caused by the trains?The noise reduction walls will diminish the noise level caused by passing trains; however, you will still be able to hear them running. Noise experts have determined the location of the noise reduction walls to ensure that all Health Canada's guidelines for acceptable sound levels will be met for all residences near the bypass. |
construction |
ConstructionWill Pie-XI Street be permanently closed?Yes, the street will be permanently closed to drivers. Roundabouts will be placed on both sides of the railway and a tunnel will be built with a pedestrian tunnel to allow for pedestrians traffic to circulate. |
construction |
ConstructionWhen will construction of the bypass begin?The project's timeline is currently under review as several steps must be completed before construction can begin, such as the Canadian Transportation Agency's (CTA) approval, land acquisition and all other necessary regulatory approvals. The Government of Canada is committed to completing this project as quickly as possible. CP and TC are working on a timeline to begin construction upon CTA approval. |
construction |
ConstructionWhy has the footprint of the project increased?The progression of engineering efforts since 2019 have enabled a better understanding of the footprint required to build the railway's bypass. The footprint now includes the space required for the construction of trenches, embankments and private crossings (bridges, tunnels, etc.), as well as wider space for construction of anti-noise walls or berms, and the installation of security fences as required. Adjustments were made to meet the operational needs of the railway operator, and for the start of construction. The footprint also includes an additional margin of approximately 5 to 10 metres to allow for minor adjustments to the design as necessary. In the end, it is possible that the footprint on some parcels will be reduced and returned to the owner. |
construction |
LandsWill there be landlocked because of the bypass?No, property owners will not have a portion of their property landlocked because of the bypass project. Where necessary, private crossings will be constructed to allow owners to access their land on the other side of the track. |
lands |
LandsWho is responsible for the maintenance of the private crossings?Maintenance of the private crossings will be under the railway operator's responsibility. |
lands |
LandsWill there be compensation for landowners who have to pay an additional amount for insurance for their private crossing?The rail operator has asked owners to modify their coverage due to new private crossings. Public Services and Procurement Canada will compensate these owners. This compensation will cover the increase in their insurance premiums. It will take the form of a single payment based on a calculation of lifetime costs. Common Canadian real estate practices were used to establish the amount of this compensation. Since the amount is unique to each owner’s situation, this compensation has not been included in the purchase offers. Owners affected by this requirement to modify insurance coverage can submit a compensation request to Public Services and Procurement Canada. They must first obtain an estimate from their insurer. |
lands |
ConstructionWhy not use an alternative corridor?The final corridor was chosen based on extensive research carried out as part of the feasibility study for the project. The chosen route allows the railway to be removed from downtown Lac-Mégantic and significantly reduces the number of residential buildings near the railway, from 265 to 8 at a distance of 100 metres from the track. This route has been recognized as the most advantageous by the Bureau d'audiences publiques sur l’environnement du Québec (BAPE) and as having the least impact on agricultural land by the Commission de protection du territoire agricole du Québec (CPTAQ). The proposed route also has many safety benefits, including a significant reduction in the number of at-level crossings (from 16 to 4), a reduced slope, and a reduction in the number of residential buildings near the railway. |
construction |